A pay application is the contractor’s monthly request to be paid for work completed and materials stored on site, built line by line from the schedule of values. In Minnesota, retainage on a private building contract is capped at 5%, so the owner’s job is to check every line against the site before signing.
Most guides to the pay application construction process are written for contractors who want their money faster. This one is written for the other side of the table: the owner who receives the pay app, has to approve it and writes the check.
What is a pay application in construction?
A pay application, or pay app, is a formal request for a construction payment as the work goes along. It shows how much of each part of the project is done, what has been paid so far, what is held back as retainage and the amount due this period.
It is not a simple invoice. An invoice says “you owe this.” A payment application asks the owner and the architect to approve the amount first, with backup to prove it. Once the architect or owner certifies it, it works as the bill.
Pay applications are used on most commercial construction projects with progress billing. They usually go out once a month, and everyone in the chain uses them. Subcontractors send theirs to the general contractor, and the general contractor rolls them into one payment application to the owner.
What is in a pay application?
Most commercial jobs use 2 standard forms from AIA Contract Documents: the AIA G702 Application and Certificate for Payment and the G703 Continuation Sheet. Some contracts use the ConsensusDocs 710 form or a custom form, but the parts are the same.
- G702 – a 1 page summary form: the original contract sum, approved change orders, total completed and stored to date, retainage, earlier payments and the current amount owed. The bottom right corner is the Certificate for Payment the architect signs
- G703 Continuation Sheet – the detailed breakdown behind the summary. Each line from the schedule of values shows its scheduled value, work completed in earlier periods, work completed this period, materials on site and balance to finish
- Schedule of values – the contract price broken into items, agreed before the first pay app. Every request is measured against it
- Supporting documents – lien waivers, change order paperwork, invoices for materials on site, insurance certificates and, on prevailing wage work, certified payroll
The G703 is filled out first, and its totals roll up into the summary. If the continuation sheet is wrong, so is the request.
How does the G702 math work?
The form takes the contract sum, measures the work done, subtracts retainage and earlier payments, and shows what is owed now. Here is an example with round numbers. It is an illustration, not a real project.
| G702 line | What it means | Example |
|---|---|---|
| 1. Original contract sum | The signed price | $2,000,000 |
| 2. Net change by change orders | Signed change orders only | $50,000 |
| 3. Contract sum to date | Line 1 plus line 2 | $2,050,000 |
| 4. Total completed and stored to date | From the G703 grand total | $820,000 |
| 5. Retainage | 5% held back on line 4 | $41,000 |
| 6. Total earned less retainage | Line 4 minus line 5 | $779,000 |
| 7. Less previous certificates | Already certified and paid | $600,000 |
| 8. Current payment due | Line 6 minus line 7 | $179,000 |
| 9. Balance to finish, including retainage | Line 3 minus line 6 | $1,271,000 |
Line 2 holds signed changes only. Anything still under discussion does not belong on the form. If you see one there, send it back. Our guide to change orders in construction covers how to check each one before it reaches a payment.
How does the monthly pay application process work?
Most contracts run on a monthly cycle with a cutoff date, a review and a due date for payment. In Minnesota, the law presumes monthly payments as the project moves forward unless the contract says otherwise.
A typical cycle on a construction project, from published industry guides:
- Cutoff – often the 25th or the last day of the month. Work done on the project through that date is billable.
- Pencil draft – on many jobs the contractor walks a rough draft with the owner’s team or the architect first, so disputes get settled before the formal request.
- Submit – the general contractor sends the application and certificate, the continuation sheet and the backup.
- Review – under the AIA A201 general conditions, the architect has a week to certify, certify a lower amount or withhold with reasons. Industry guides put the full owner and architect review at 1 to 2 weeks.
- Payment – on the agreed terms, often a month after certification.
A missing document restarts the clock. One subcontractor’s late waiver can hold a billing cycle for 2 to 4 weeks, according to Built. Our comparison of an owner’s rep vs construction manager vs general contractor explains who works for whom.
What should an owner check before approving a pay application?
Check that the percent complete on each line matches what is built on the project, that only signed change orders are billed, that the holdback is figured right and that every required waiver is attached. A pay app can be correct on paper and still bill for work that is not in place.
| Check | What to look for | Why it matters |
|---|---|---|
| Percent complete | Walk the site. Does work billed at 60% look 60% done? | Overbilling leaves you exposed if the contractor walks away |
| Front-loading | High values on early items such as mobilization, general conditions and site work | Early cash pulled forward leaves too little to finish the later work |
| Materials on site | Invoices, photos, insurance and, for off site storage, a bill of sale | You are paying for materials that are not yet installed |
| Change orders | Each one on line 2 has a signed approval | Unsigned changes do not belong on the bill |
| Retainage | Right percentage, figured on the right base | A math slip compounds every month |
| Lien waivers | One from the general contractor and each sub and supplier billing this period | Protects your property from a claim for work you already covered |
| Previous certificates | Line 7 matches what you actually sent | Catches double billing |
Front-loading is the one owners miss most. Contractors who set high values on the first items of the schedule can collect cash ahead of the work. Built and Ramp both flag inflated mobilization and general conditions as the classic sign. The time to catch it is when the schedule of values is first submitted, before the first pay app.
A payment is not approval of the work. Minnesota law says so directly: a progress payment does not count as acceptance of any work or a waiver of defects. Still, it is easier to fix a problem on a project before the money goes out.
What is retainage, and how much can you hold in Minnesota?
Retainage is a share of each payment the owner holds back until the project is done, so the contractor has a reason to finish the punch list and closeout. Industry guides put it at 5% to 10%, but in Minnesota a private building and construction contract may not hold more than 5%.
Here is what Minnesota Statutes section 337.10 says about private building contracts:
| Rule | What it says |
|---|---|
| Payment schedule | Monthly as the project moves forward, unless the contract says otherwise, based on work completed as approved by the owner |
| Retainage cap | No more than 5%. The owner may reduce it or drop it if the work is going well, and nothing in the law requires a holdback at all |
| Release | Everything held must be released within 60 days after substantial completion |
| After substantial completion | The owner may hold no more than 250% of the cost to finish or fix known work, plus the greater of 1% of the contract or $500 until final paperwork is in |
| Warranty work | Money may not be held back for warranty work |
| Subcontractors | Owed payment within 10 days after the contractor receives money for undisputed work. Late undisputed amounts carry interest of 1.5% per month, and the unpaid party may stop work |
| Public work | This part of the law does not apply to public agencies, which follow their own rules |
If you keep money back after substantial completion, a written statement of the amount and the reason is required by the statute. This is general information, not legal advice. Have your attorney read the payment terms before you sign.
Why do lien waivers matter with every payment?
A lien waiver is a signed statement from a contractor, subcontractor or supplier giving up the right to file a mechanics lien for the amount covered. Without one, you can pay your general contractor in full and still face a lien from a sub who never saw the money.
There are 2 kinds. A conditional lien waiver takes effect once the payment actually clears. An unconditional waiver takes effect when signed, so it should only follow money that has been received. In Minnesota, a contract term that makes someone give up lien rights before being paid is void, so conditional waivers travel with the pay app and unconditional ones follow the payment.
The law also gives the owner some protection. Under section 514.07, the owner may hold back enough of the price to cover lien claims from subs and suppliers, and does not have to pay the contractor until 120 days after completion except to the extent the contractor provides signed waivers. At final payment, the AIA G706 and G706A affidavits are the usual closeout documents.
Should you pay a contractor 50% upfront?
No, not on a commercial project. On commercial work, payment follows work in place through monthly pay apps, and the builder’s startup costs show up as a mobilization entry on the schedule of values.
Large upfront deposits are mostly a residential habit. Levelset reports deposits running from about 10% on large multi-stage projects to as much as 50% on small ones, and calls anything above 50% unreasonable. A commercial owner who pays half the contract before the ground is broken has given up the main protection of progress billing: you only pay for what is built.
There are fair exceptions. A long lead item such as switchgear, a generator or a steel package may require a deposit to hold a production slot. Treat it as stored materials or a specific written term with invoices, proof of the order and, if possible, title to the equipment. The Minnesota statute backs this up: nothing in it requires payment for work that is not complete or has not been invoiced.
How does an owner’s rep help with pay applications?
An owner’s rep reads every pay app for the owner, walks the project site to check the percent complete, chases the missing waivers and recommends what to approve. You sign knowing what you are paying for.
That is how Inventure works on owner’s rep jobs. We work only for the owner, with no stake in the construction contract, and we read every bid, pay application and change order before you sign. Doug Boser was on the construction side of the table from 1989 and founded Boser Construction in 1996 before he switched to the owner’s side in 2000. He knows how contractors build a schedule of values because he used to build them.
If you are weighing the cost, see how much an owner’s representative costs and when to hire an owner’s representative. The best time is before design begins, but a second set of eyes on every request pays off on any project already under way. You can see the kind of work we do on our projects page, and learn more about our owner’s representation service.
Building in St. Cloud or anywhere in Central Minnesota? Tell us what you are building or call (320) 980-2300. For a checklist you can keep, get the Owner’s Building Playbook.
Frequently asked questions
A pay app is the contractor’s monthly request for a construction payment. It lists the work completed and materials on site for each part of the schedule of values, subtracts the holdback and earlier payments, and shows the amount owed. Most use the AIA G702 and G703 forms.
The G702 is the 1 page application and certificate for payment. The G703 Continuation Sheet is the detail behind it, one line per item on the schedule of values. The G703 totals roll up into the G702.
On commercial work, owners usually make monthly progress payments against approved pay applications, minus retainage. Use a check or bank transfer against the certified request, and collect a waiver with each payment. Avoid cash, which leaves no clear record of what you covered.
On a private building and construction contract in Minnesota, retainage may not exceed 5%. The owner must release it within 60 days after substantial completion, with limited holdbacks for unfinished work and final paperwork. Public work follows separate rules.
The standard AIA G702 form includes a contractor signature block that is notarized. The parties can agree in the contract to drop notarization. Follow what your contract requires.
An owner can certify a lower amount or withhold payment for good reason, such as work that is not in place, unsigned changes or missing waivers. Under the AIA documents, the architect states the reasons in writing. Release the items nobody disputes on time, and hold back only the ones in question.