Change Orders in Construction: How Owners Keep Them Under Control

Two people in hard hats seen from behind, looking at building drawings on a plywood table inside a commercial building with metal stud framing and exposed ductwork

Change orders in construction are written amendments to a signed contract that change the scope of work, the price, the schedule or all 3. Research cited by Smartsheet puts change order costs at 10% to 15% of the contract value on major projects, so an owner who reads each one before signing protects real money on any construction project.

Most guides on this topic are written for contractors who want to get paid for extra work. This one is written for the person who pays: the business owner putting up a clinic, a bank, an office or a production building. It covers what a change order is, why they happen, how they are priced and what to check before your signature goes on one.

What is a change order in construction?

A change order is a signed document that amends the original contract after construction has started. It states what work is added, removed or changed, what that does to the price and how many days it adds to or takes off the schedule.

Once the owner, the contractor and usually the architect sign it, the change order carries the same weight as the original contract. That is the point to remember. A change order is not a note in a meeting or a text from the job site. It is a contract amendment, and it deserves the same attention you gave the contract itself.

A change order can also lower the price. When scope is removed or a less costly material is approved, the result is a deductive change order, and the credit should be as carefully priced as any added cost.

Why do change orders happen?

Change orders happen because no set of drawings predicts everything, and because owners change their minds. Almost every cause falls into 1 of 5 groups.

CauseExampleWhat the owner should ask
Owner requested changesAdding rooms, upgrading finishes, moving walls after work beginsDo we need this now, and what does it do to the schedule?
Unforeseen site conditionsPoor soil, rock, buried utilities, hidden damage in an existing buildingWhat did the soil report and survey show, and what does the contract say about hidden conditions?
Design errors and omissionsDrawings that conflict, a missing beam, a detail that was never drawnWas this in the drawings the contractor bid on?
Code and inspector requirementsNew rules or an inspector’s order, such as added sprinklersIs it truly required, and who should have caught it in design?
Material and schedule problemsA product that is no longer available, late owner supplied items, severe weatherIs there an equal product at the same price?

The first group is the one you control completely. Every change you ask for after the contract is signed is priced without competition, so decide as much as you can while the building is still on paper.

What are the types of change orders?

There are 3 main documents used to change the work, and only 1 of them is a true change order. The standard AIA contract forms name them this way.

DocumentWhat it doesChanges price or time?
Change orderOwner, contractor and architect agree on the change, the cost and the timeYes, and all parties sign
Construction change directiveThe owner and architect direct the work to proceed before cost and time are agreedYes, settled later in a change order
Architect’s supplemental instructionA minor clarification of the drawingsNo

A construction change directive keeps the project moving when the 2 sides cannot agree on a number. It also means the final cost is open until a change order closes it. Use directives rarely, and ask the contractor to track labor, material and equipment for that work every day.

You will also hear the terms additive and deductive. An additive change order adds scope and usually cost or time. A deductive one removes scope and should return money to the owner.

How does the change order process work?

The change order process should be written into the contract before construction starts, and it follows the same 6 steps on most projects, large or small.

  1. Someone identifies the change. The owner, the architect or the contractor flags it in writing, often after a request for information about the drawings.
  2. The contractor prices it. The proposal describes the work and breaks the cost into labor, material, equipment, subcontractor costs, and overhead and profit.
  3. The time impact is stated. Every proposal should say how many days it adds, even when the answer is 0.
  4. The owner’s side reviews it. The architect and the owner’s representative check the scope against the contract and the price against the market.
  5. The parties negotiate and sign. Approval is only real once the signatures are on the document, so no step in the process is skipped.
  6. The work starts and the records are updated. The contract price, the schedule and the change order log all change on the same day.

The rule that protects both sides is simple: no signed change order, no extra work. Contractors are told the same thing by their own trade groups, because unwritten changes are the ones that end in a payment dispute.

What should a change order include?

A complete change order shows its math. If any of the items below are missing, send it back before you sign.

  • Project and contract information – the project name, the parties and a change order number
  • Description of the change – exactly what is added, removed or changed, with drawing references
  • Reason for the change – owner request, site conditions, a design issue or a code requirement
  • Cost breakdown – labor, material, equipment, subcontractors, overhead and profit
  • Schedule impact – days added or removed and the new completion date
  • Updated contract price – the original contract amount, all earlier change orders, this one and the new total
  • Signatures – every signature the contract requires, with dates

A lump sum with no breakdown fails this test, and so does a document with no dates. You cannot tell if a single number is fair, and neither can your lender.

How are change orders priced?

Change orders are priced as a lump sum, on time and materials, or with unit prices set in the contract. Then the contractor adds a markup for overhead and profit.

Pricing methodHow it worksBest for
Lump sumA fixed price backed by a cost proposalWork that is clearly defined
Time and materialsActual labor, material and equipment plus a feeWork that is still being discovered
Unit pricesRates agreed in the contract, such as a price per cubic yard of soilQuantities nobody can know in advance

The markup is where owners should look closely. Trade publications put the allowed overhead and profit markup on change orders at 10% to 15% of the direct cost on most commercial contracts, and Trimble notes the percentages are often set in the contract documents. If your contract is silent, the contractor sets that percentage after you have lost your ability to shop the price.

Set 3 things in the contract before you sign it: the markup on changes for the general contractor, the markup the general contractor may add on top of a subcontractor’s price, and unit prices for the items most likely to change.

How much do change orders add to a project?

On major projects, research cited by Smartsheet found change orders typically add 10% to 15% of the contract value. Your project may land well under that, or over it, and the gap usually comes down to how complete the design was on bid day.

Plan for this in the budget. Hold an owner’s contingency that the contractor cannot spend without your approval, and treat every change order as a draw against that contingency. When the contingency is going down faster than the building is going up, you have a warning while there is still time to act.

Changes also cost time. The same research found that a high number of changes can cut productivity by 10% to 30%, because crews stop, wait and return. While the schedule slips, you carry rent, loan payments and payroll on a building you cannot use.

How can an owner keep change orders under control?

An owner keeps change orders under control by deciding early, writing the rules into the contract and reading every change before signing it. None of that requires a construction background. It requires discipline.

  • Finish the design before you bid. Loose plans are the largest source of changes on a project. Walk the plans with the people who will use the building.
  • Test the site first. Soil borings and a survey cost little next to an unforeseen conditions claim.
  • Write the process into the contract. Name who can approve a change, how fast, and what markup applies.
  • Be careful with every allowance. An allowance is a placeholder for work that was not priced. If the real cost comes in higher, the difference arrives as a change order.
  • Keep a change order log. List every proposed, pending and approved change with its cost and days, and review it at each project meeting with the project team.
  • Match changes to payment. A change order should appear on a pay application only after it is signed.
  • Say no to verbal approvals. A quick yes on a site walk can waive the protection your contract gave you.

What should you check before you sign a change order?

Before you sign, confirm the work is truly outside the original contract and that the price and time are both fair. These 7 questions catch most problems.

  1. Is this work already shown in the drawings or the scope of work?
  2. Who caused the change, and does the contract make that party responsible for the cost?
  3. Does the cost breakdown show quantities, hours and rates you can check?
  4. Does the markup match what the contract allows?
  5. If scope was removed, is the credit as large as the cost would have been?
  6. Does it state the days added, and does it close out all time claims for this change?
  7. Does the new contract total match your own log?

Change orders signed unread are one of the most common ways a building budget slips. Each one may look small. Together they decide if the project finishes on budget.

Who reviews change orders for the owner?

The architect reviews change orders on most commercial projects, and an owner’s representative reviews them only for you. The difference matters when the change traces back to the drawings.

An architect is asked to rule on changes that may come from the architect’s own design errors. The contractor wrote the price. The owner is the only party at the table with no construction staff. An owner’s representative fills that seat. We compare the 3 roles in owner’s rep vs construction manager vs general contractor.

On our owner’s rep work, Inventure works only for the owner. We have no stake in the construction contract and no loyalty to any contractor or subcontractor. We read every bid, pay application and change order before you sign.

Doug Boser, our CEO, has been on the construction side of the table since 1989 and on the owner’s side since 2000. He founded Boser Construction in 1996 before he started Inventure, so he knows how a contractor prices a change and where the soft numbers sit. Because we get involved before design begins, many changes are settled on paper, when they cost the least. If you are weighing the cost of that help, see how much an owner’s representative costs and when to hire one.

What causes change orders in Central Minnesota?

In Central Minnesota, the ground, the weather and city requirements cause many of the changes an owner did not ask for. All 3 can be planned for.

  • The ground. Soil conditions change from one lot to the next. Borings before you buy tell you what the foundation needs.
  • The season. Work that slides into winter can bring heating, frost protection and snow removal costs that nobody carried in the budget. A schedule built around the Minnesota construction season avoids many of them.
  • The city. Approvals in St. Cloud, Sartell, Sauk Rapids and Waite Park can come with conditions, such as utility or site work the drawings did not show. Meeting city staff before design is finished keeps those items in the bid instead of in a change order.

For a wider look at budgets, see what it costs to build a commercial building.

Planning a new building, an expansion or a move? Tell us what you are building or call (320) 980-2300. Want to see our work first? Browse our projects, or download the Owner’s Building Playbook.

Frequently asked questions

Under what conditions can change orders occur in construction contracts?

A change order can occur any time work falls outside the original contract after it is signed. The common conditions are owner requests, unforeseen site conditions, design errors, code requirements and material problems. The contract’s changes clause sets the rules for each.

How do you do a change order?

Put the change in writing, have the contractor price it with a full cost breakdown and state the schedule impact. The architect and the owner review it, negotiate if needed and sign. Work on the change should start only after the document is signed.

What are changes called in construction?

An agreed change is called a change order. A change the owner directs before the price is settled is a construction change directive, and a minor clarification with no cost is an architect’s supplemental instruction. Contractors also use the term extra work.

What is a change order in project management?

In project management, a change order is the formal record that the scope, budget or schedule of a project has been changed with approval. In a construction project it is also a legal amendment to the contract, which is why it needs signatures.

Can a contractor refuse a change order?

Usually not, if the change is within the general scope of the project. Most contracts let the owner order changes as long as the contractor is paid for added cost. A contractor can refuse a change so large that it becomes a different project, which courts call a cardinal change.

Can work start before a change order is signed?

It should not. Extra work that starts on a verbal approval leaves the price and the time open, which is how disputes begin. If the schedule cannot wait, use a written construction change directive and track the costs daily until a change order closes it.

1 Comment

  1. […] under discussion does not belong on the form. If you see one there, send it back. Our guide to change orders in construction covers how to check each one before it reaches a […]