Design-Build vs Design-Bid-Build: Which Fits Your Building?

Steel frame of a single-story commercial building going up on a concrete slab in autumn, with a mobile crane lifting a beam and 2 workers in hard hats reviewing rolled drawings on a pickup truck

Design-bid-build uses 2 separate contracts in a row: you hire an architect to finish the design, then contractors bid on it and the lowest qualified contractor builds it. Design-build uses 1 contract with 1 firm that designs and builds, so the work can overlap and the project usually finishes sooner, but you give up the independent check between designer and builder.

That is the short answer to design build vs design bid build. The longer answer depends on a question most guides skip, because most are written by design-build firms: in each project delivery method, who is looking out for the owner? Doug Boser, Inventure’s CEO, was on the construction side of the table from 1989 and has been on the owner’s side since 2000. This guide is written from the owner’s seat.

What is the difference between design-build and design-bid-build?

The difference is how many agreements you sign and when the builder joins the project. In the traditional approach the owner holds 2 contracts and the contractor joins after the design is done. In design-build the owner holds 1 contract and the builder is on the team from day 1.

Design-bid-buildDesign-build
Agreements2: owner to architect, owner to contractor1: owner to design-builder
Who the architect works forThe ownerThe design-builder
When the builder joinsAfter the construction documents are doneAt the start of design
ScheduleDesign, bid and construction phases in sequenceDesign and construction phases overlap
How the price is setCompetitive bids on a finished designEstimates during design, then a negotiated price
Who sorts out design vs construction problemsThe owner, in the middleThe design-builder
Best fitFixed design, price competition, public procurement rulesTight schedule, early cost input, 1 point of accountability

Neither delivery method is better for every project. The right one depends on your project schedule, how settled your plans are, and how much time you have to manage the construction project yourself.

What is design-bid-build?

Design-bid-build is the traditional project delivery method, and it still runs most public construction projects. The owner hires an architect, the drawings are finished, contractors bid on them, and the owner signs a separate agreement with the winning general contractor.

How the 3 steps work

  • Design – you sign an owner-architect agreement, often on AIA Contract Documents forms. The architect and engineers turn your needs into a full set of construction documents
  • Bid – general contractors price the documents with their subcontractors. Because every bidder prices the same drawings, the bids are easy to compare, and the bidding process stays open to multiple firms. Public procurement typically sends the work to the lowest responsible bidder
  • Build – you sign an owner-contractor agreement and construction begins. The designer often stays on to answer questions and review the monthly pay requests

The strength of this approach is separation. The architect works for you, not the builder, so you have a professional on your side who reviews the work against the design. The weakness is that the builder’s knowledge arrives late in the process. Builders see the drawings only when it is time to bid. Constructability problems and budget gaps often surface only when bids come in. If they come in over budget, you pay to redesign and rebid, and you lose time.

What is design-build?

Design-build is a project delivery method where 1 firm holds a single contract for both design and construction. The design-builder employs the architect or hires one under its own agreement, so designers and builders answer to the same company.

The Design-Build Institute of America (DBIA) calls the single contract the basic difference between design-build and all other project delivery methods. It is now the fastest growing approach in the United States: DBIA cites an FMI forecast that design-build will be over 47% of construction spending by 2028.

The process usually starts with the owner setting goals, a budget and a rough scope, then choosing a team through a request for qualifications or a request for proposals. That procurement step can weigh qualifications, price or both. The integrated team develops the project design and the price together, and construction can start on early packages, like site work and foundations, while the rest of the project is still being drawn. Supporters point to closer collaboration between design and construction inside 1 integrated team, simpler communication and fewer change orders.

Is progressive design-build the same as design-build?

Progressive design-build is a version of the design build method, not a different delivery method. DBIA describes it this way: you pick the team mostly on qualifications, then you work the design and the cost model forward together until you agree on a price.

The other common version is 2 step best value procurement. You shortlist the most qualified teams first, then ask them for design and price proposals and pick the best overall value. Progressive gives the owner more say and more collaboration in the design. Best value gives you more price competition up front.

Is design-build faster than design-bid-build?

Yes, usually by a wide margin. In the 2018 study by the Construction Industry Institute and the Charles Pankow Foundation, design-build projects were delivered 102% faster from design to completion and built 36% faster during construction than design-bid-build projects, as summarized by DBIA. The study looked at 212 projects.

The time comes from overlapping phases. In the traditional process, nothing gets built until the design is finished and the bidding is done. With the design build method, the team can release the site and foundation package while the interior is still on the drawing board.

That speed is only worth something if the design and construction teams can keep up. Construction moving ahead of the drawings means some decisions get made with less information. And no delivery method moves a city council meeting, a permit review or a long wait on equipment, so completion still depends on those dates. Faster delivery also means fewer months of carrying costs on a construction project you cannot use yet.

Is design-build more expensive than design-bid-build?

Not on average, but it depends on how the price is set. The same study found design-build projects had 0.3% lower unit cost, 3.8% less cost growth and 1.7% less schedule growth than design-bid-build. Those are averages from 212 projects, not a promise for your project.

The traditional approach gives you something design-build cannot: multiple contractors bidding against the same finished drawings. That price competition is real. What it does not protect you from is the gap between drawings and field conditions, which shows up during construction as change orders. If the drawings miss something, the contractor prices the fix and the owner pays it. Our guide to change orders in construction covers how those costs add up.

Design-build trades open bidding for early cost input. The builder prices the design as it develops, so you hear about a budget problem early, not after bids. The risk is that you negotiate with 1 firm and have no second number to test it against. For what moves cost per square foot, see what it costs to build a commercial building.

When does a design-build price become binding?

An estimate is not a price. A design-build price becomes binding only when you sign a pricing commitment, usually a lump sum or a guaranteed maximum price, after the drawings are far enough along to define the scope. Before you sign and before construction starts, get in writing:

  • What the price includes, and the drawings and specifications it is based on
  • The pricing type, and what happens to any savings under a cap
  • Every project allowance and contingency, and who decides when it is spent
  • Who pays when the team’s own design has an error, since there is no separate design firm to answer for it

Who carries the risk, and who protects the owner?

In design-bid-build delivery, the owner carries more risk but has an architect on their side. In design-build, the design-builder carries more risk, but nobody on the team works only for the owner. That is the part most comparisons leave out.

Communication runs through the owner on a design-bid-build project, so problems often fall between the 2 contracts. The contractor says the drawings were wrong, the design firm says the work was built wrong, and the owner is in the middle, paying both while the schedule slips and rent, interest and payroll keep running on a building you cannot use. Most owners do not have the time to referee that.

The design build method fixes that with a single point of responsibility. If design and construction do not match, it is 1 company’s problem. But that also means the architect reviewing the work is on the same payroll. The person who checks the pay application works for the company sending it.

This is where owner’s representation fits. An owner’s rep works only for you on either delivery method, has no stake in the construction contract and reads every bid, pay application and change order before you sign. On design-bid-build, the rep manages the 2 contracts and keeps collaboration between the architect and contractor going through construction. On design-build, the rep is the independent check the method leaves out. Our comparison of an owner’s rep vs a construction manager vs a general contractor explains where each role sits, including construction manager at risk.

How much control does the owner keep over the design?

You keep the most direct control with design-bid-build, because the architect works for you and the plans are settled before anyone prices them. With design-build you still approve the design, but you approve it through the design-builder during design and construction. That is the trade: more control and more work for you, or less work and less direct control.

Design-build depends on collaboration, but the collaboration happens inside 1 company. It does not mean the contractor picks your finishes. Your agreement sets your approval rights, and you still set the goals, standards and budget. What changes is who the designer is loyal to. When a design choice costs the firm money, an architect inside a design-build team may not push for your preference the way your own architect would.

If a project has to look a certain way, fit a tight site or meet strict rules, like a clinic, a bank or a church, many owners want their own architect. If the project is simpler, like a warehouse or production building where speed matters more than appearance, design-build often makes more sense.

Which delivery method fits your building?

Choose design-bid-build when the plans must be settled before you price them, and choose design-build when schedule and early cost input matter more. Use this table to pick an approach. Of the common delivery methods, these 2 are the ones most owners weigh first.

Choose design-bid-build whenChoose design-build when
You want your own architect and full design controlYou want 1 agreement and 1 point of accountability
Public procurement rules or your board require competitive bidsSchedule is the top priority
The scope is simple and fully definedYou want builder cost and constructability input before the design is done
You can wait for a full design and bid periodYou can make decisions quickly during design
You have staff or an owner’s rep to run 2 agreementsYou have someone independent to check the design-builder

Either approach works when the owner is involved early in the process. The biggest budget decisions on any project happen before design begins: site, size, building type and what you can live without. Our guide on when to hire an owner’s representative explains why the first months set the cost.

What changes for a project in Central Minnesota?

In Minnesota, the construction season is the deadline nobody can negotiate. Getting footings in and the shell enclosed before frost decides the completion date, or whether a project waits out a winter, and that pushes many owners toward overlapping phases. Most builders here plan the year around that window.

With the traditional process, a bid that comes in over budget in spring can mean redesign and rebid, and a ground breaking that slides from May into fall. With design-build, the team can release site work for the project early.

Either way, city approvals stay with the owner. In St. Cloud, Sartell, Sauk Rapids and Waite Park, site plan review, a PUD if you need one and water and sewer access charges all go through the city approval process, no matter who holds the construction contract. Our timeline for a build-to-suit walks through that calendar month by month.

Inventure sits across from the city, the architect and the contractor on the owner’s behalf, so the delivery approach and the construction schedule serve your project and not the other way around.

Frequently asked questions

Is design-build better than design-bid-build?

Neither approach is better for every project. Design-build is usually faster and has less cost growth on average, according to the 2018 CII and Pankow study. Design-bid-build gives you your own architect and competitive bids on a finished design, which is why owners still use it on public work.

What does design-build mean?

Design-build means 1 company holds a single contract to both design and build your project. The architect and engineers work inside that company’s integrated team, so the owner deals with 1 point of responsibility for the whole project instead of 2.

What are the 4 types of construction contracts?

People usually mean the 4 common ways to set the price: lump sum, cost plus a fee, guaranteed maximum price, and time and materials. The 4 common delivery methods are a different list: design-bid-build, design-build, construction manager at risk and construction manager as adviser.

What is the difference between design-build and EPC?

EPC stands for engineering, procurement and construction. It is a form of design-build used mostly on industrial plants and energy projects, where 1 contractor designs, buys the equipment and delivers a working facility, often for a fixed price. Commercial buildings usually use standard design-build instead.

Can you hire an owner’s rep on a design-build project?

Yes, and it is when one is most useful. The architect works for the design-builder, so an owner’s rep gives you someone who reviews the price, the drawings, every pay application and every change order for you alone, from design through construction.

Talk to someone on your side of the table

Picking a project delivery method is one of the first big decisions on a new building. Whether you lean design-build vs design-bid-build, the choice is easier to change before design begins than after. Tell us what you are building on our contact page or call (320) 980-2300 to talk with Doug. You can see the kinds of work we do on our projects page, or get the Owner’s Building Playbook first.